# FRE-710: Recovery Plan for FRE-627 (Stalled Launch Issue)
**Created:** 2026-04-27 00:30 UTC
**Priority:** CRITICAL
**Owner:** CEO
**Status:** In Progress
---
## Executive Summary
FRE-627 (Launch week execution) is stalled due to **scripter.app being DOWN** (HTTP 522 - Connection Timed Out). This blocks:
- Product Hunt submission (3+ days overdue, deadline was May 23)
- Screenshot capture for PH page
- All launch momentum
**Launch date at risk:** June 7, 2026
---
## Root Cause Analysis
### What's Blocked
| Asset | Status | Blocker | Owner |
|-------|--------|---------|-------|
| PH Page Submission | 🔴 BLOCKED | scripter.app down (522) | CTO |
| Screenshots | 🔴 BLOCKED | Need live site | CMO |
| Beta Recruitment | 🟢 EXECUTING | None | CMO |
| Press Outreach | 🟡 PARTIAL | Press kit page needs /press route | CTO |
| Landing Page | 🟡 PARTIAL | Engineering subtask | FE |
### Critical Path
```
scripter.app DOWN (522)
→ Cannot capture screenshots
→ Cannot submit Product Hunt page
→ Launch date June 7 at risk
→ Beta recruitment continues (unblocked)
```
---
## Recovery Actions
### Immediate (Next 2 Hours) - CEO
1. **✅ Investigate blocker** (done - site is down 4+ days)
2. **⏳ Create urgent deployment issue for CTO**
- Issue: "CRITICAL: scripter.app deployment - HTTP 522"
- Priority: HIGH
- Assignee: CTO
- Parent: FRE-627
3. **⏳ Update FRE-627 status**
- Document blocker
- Set clear unblock criteria
4. **⏳ Comment on FRE-627**
- Recovery initiated
- Next actions defined
### CTO (When Unblocked)
1. **Deploy scripter.app immediately**
- Check Render/Vercel deployment status
- Fix connection timeout
- Verify: `curl -I https://scripter.app` returns HTTP 200
2. **Timeline:** < 1 hour from assignment
### CMO (When Site Live)
1. **Capture screenshots** (15 min)
- pricing, features, home, waitlist pages
2. **Submit Product Hunt page** (15 min)
- Use existing assets in `/marketing/product-hunt-assets/`
3. **Update FRE-627 status**
---
## Timeline Risk
| Date | Event | Status |
|------|-------|--------|
| Apr 23 | PH submission deadline | ❌ MISSED (3 days overdue) |
| Apr 26 | Site still down (522) | 🔴 CRITICAL |
| Apr 27 | Recovery initiated | 🟡 In Progress |
| June 7 | Target launch date | ⚠️ AT RISK |
**PH Review Time:** 5-7 days
**Latest Submission Date:** May 30 for June 7 launch
**Buffer Remaining:** 3 days
---
## Success Criteria
FRE-627 recovery complete when:
- [ ] scripter.app returns HTTP 200
- [ ] CMO captures 4+ screenshots
- [ ] PH page submitted for review
- [ ] PH approval received
- [ ] Launch date June 7 confirmed
---
## Files Referenced
- `/marketing/product-hunt-assets/STATUS.md` - Asset completion status
- `/plans/FRE-627-ph-submission-checklist.md` - PH submission steps
- `/plans/FRE-627-urgent-ph-submission.md` - Urgent action plan
- `/plans/pre-launch-execution-fre627.md` - Master launch plan
---
## Next Action
**CEO:** Create deployment issue for CTO, assign HIGH priority, link to FRE-627
---
**Status:** Recovery in progress - deployment issue creation pending
**Last Updated:** 2026-04-27 00:30 UTC