@@ -12,7 +12,7 @@ Beta program setup planning complete. All infrastructure documents created and r
|
||||
|
||||
1. **Master beta program plan** - `/plans/FRE-647-beta-program-setup.md`
|
||||
- 500 user target across 5 channels
|
||||
- 3-week timeline (April 26 - May 16)
|
||||
- 3-week timeline (May 26 - June 16)
|
||||
- Success metrics defined
|
||||
|
||||
2. **Beta signup form** - `/marketing/beta-signup-form.md`
|
||||
@@ -28,7 +28,7 @@ Beta program setup planning complete. All infrastructure documents created and r
|
||||
4. **Reddit recruitment** - `/marketing/reddit-beta-recruitment.md`
|
||||
- Main post for r/Screenwriting
|
||||
- AMA response templates
|
||||
- Posting schedule (May 3-9)
|
||||
- Posting schedule (June 3-9)
|
||||
|
||||
5. **Execution checklist** - `/plans/FRE-647-execution-checklist.md`
|
||||
- 50+ actionable tasks
|
||||
@@ -49,9 +49,9 @@ Beta program setup planning complete. All infrastructure documents created and r
|
||||
| Phase | Dates | Target | Status |
|
||||
|-------|-------|--------|--------|
|
||||
| Infrastructure | Apr 26-27 | Mailchimp, Discord, Forms | 🟡 In progress |
|
||||
| Influencer outreach | Apr 26-May 2 | 50 contacts, 10 commitments | 🟢 Ready |
|
||||
| Community (Reddit) | May 3-9 | 200 contacts, 40 signups | ⏳ Pending |
|
||||
| Film schools | May 10-16 | 100 contacts, 20 commitments | ⏳ Pending |
|
||||
| Influencer outreach | Apr 26-June 2 | 50 contacts, 10 commitments | 🟢 Ready |
|
||||
| Community (Reddit) | June 3-9 | 200 contacts, 40 signups | ⏳ Pending |
|
||||
| Film schools | June 10-16 | 100 contacts, 20 commitments | ⏳ Pending |
|
||||
| Beta management | Ongoing | Weekly surveys, NPS >50 | ⏳ Pending |
|
||||
|
||||
---
|
||||
|
||||