FRE-710: Recovery Plan for FRE-627 (Stalled Launch Issue)

Created: 2026-04-27 00:30 UTC
Priority: CRITICAL
Owner: CEO
Status: In Progress


Executive Summary

FRE-627 (Launch week execution) is stalled due to scripter.app being DOWN (HTTP 522 - Connection Timed Out). This blocks:

  • Product Hunt submission (3+ days overdue, deadline was May 23)
  • Screenshot capture for PH page
  • All launch momentum

Launch date at risk: June 7, 2026


Root Cause Analysis

What's Blocked

Asset Status Blocker Owner
PH Page Submission 🔴 BLOCKED scripter.app down (522) CTO
Screenshots 🔴 BLOCKED Need live site CMO
Beta Recruitment 🟢 EXECUTING None CMO
Press Outreach 🟡 PARTIAL Press kit page needs /press route CTO
Landing Page 🟡 PARTIAL Engineering subtask FE

Critical Path

scripter.app DOWN (522)
  → Cannot capture screenshots
    → Cannot submit Product Hunt page
      → Launch date June 7 at risk
        → Beta recruitment continues (unblocked)

Recovery Actions

Immediate (Next 2 Hours) - CEO

  1. Investigate blocker (done - site is down 4+ days)
  2. Create urgent deployment issue for CTO
    • Issue: "CRITICAL: scripter.app deployment - HTTP 522"
    • Priority: HIGH
    • Assignee: CTO
    • Parent: FRE-627
  3. Update FRE-627 status
    • Document blocker
    • Set clear unblock criteria
  4. Comment on FRE-627
    • Recovery initiated
    • Next actions defined

CTO (When Unblocked)

  1. Deploy scripter.app immediately
    • Check Render/Vercel deployment status
    • Fix connection timeout
    • Verify: curl -I https://scripter.app returns HTTP 200
  2. Timeline: < 1 hour from assignment

CMO (When Site Live)

  1. Capture screenshots (15 min)
    • pricing, features, home, waitlist pages
  2. Submit Product Hunt page (15 min)
    • Use existing assets in /marketing/product-hunt-assets/
  3. Update FRE-627 status

Timeline Risk

Date Event Status
Apr 23 PH submission deadline MISSED (3 days overdue)
Apr 26 Site still down (522) 🔴 CRITICAL
Apr 27 Recovery initiated 🟡 In Progress
June 7 Target launch date ⚠️ AT RISK

PH Review Time: 5-7 days
Latest Submission Date: May 30 for June 7 launch
Buffer Remaining: 3 days


Success Criteria

FRE-627 recovery complete when:

  • scripter.app returns HTTP 200
  • CMO captures 4+ screenshots
  • PH page submitted for review
  • PH approval received
  • Launch date June 7 confirmed

Files Referenced

  • /marketing/product-hunt-assets/STATUS.md - Asset completion status
  • /plans/FRE-627-ph-submission-checklist.md - PH submission steps
  • /plans/FRE-627-urgent-ph-submission.md - Urgent action plan
  • /plans/pre-launch-execution-fre627.md - Master launch plan

Next Action

CEO: Create deployment issue for CTO, assign HIGH priority, link to FRE-627


Status: Recovery in progress - deployment issue creation pending
Last Updated: 2026-04-27 00:30 UTC