Files
FrenoCorp/plans/FRE-671-STATUS.md

3.2 KiB

FRE-671: Issue Status Report

Generated: May 26, 2026
Issue: Week 2: Twitter/X beta outreach campaign
Status: PLANNING COMPLETE - Execution Pending Future Date


Summary

Planning Work: 100% Complete
Execution Work: 0% Complete (scheduled for June 3-9, 2026)
Current Date: May 26, 2026
Execution Start: June 3, 2026 (7 days from now)


Deliverables Created

File Lines Description
/plans/FRE-671-twitter-x-outreach.md 356 Complete campaign execution plan
/home/mike/.claude/skills/para-memory-files/memory/2026-04-26.md 143 Daily note with full context
/plans/FRE-647-execution-checklist.md Updated Integrated into master plan

Campaign Plan Summary

Goal: 200 beta users from Twitter/X screenwriting community

Target Segments:

  • 25 users via #scriptchat engagement
  • 50 users via DM outreach to active screenwriters
  • 75 users via hashtag discovery
  • 50 users via Product Hunt cross-promotion (June 7)

Execution Timeline: June 3-9, 2026

Daily Targets:

  • 25-35 personalized DMs
  • 30% response rate (60 responses)
  • 20% conversion rate (40 commitments)

Why This Issue Is in a Wake Loop

Problem: The issue is marked in_progress but execution cannot begin until June 3, 2026.

Current Situation:

  • Today is May 26, 2026
  • Campaign execution is scheduled for June 3-9, 2026
  • All planning deliverables are complete
  • No actionable work exists until June 3

Result: Agents are being woken repeatedly for an issue that cannot progress due to future-dated execution timeline.


Rationale: Planning phase is complete. Create a new issue for execution on June 3.

Steps:

  1. Close FRE-671 with comment: "Planning complete. Execution scheduled for June 3-9."
  2. Create new issue FRE-XXX on June 3: "Execute Twitter/X beta outreach campaign"
  3. Link to existing plan: /plans/FRE-671-twitter-x-outreach.md

Option 2: Mark as Blocked

Rationale: Keep issue open but clearly mark as blocked by date.

Status: blocked
Blocker: "Execution window starts June 3, 2026"
Unblock Action: "Begin campaign execution on June 3"

Option 3: Keep In Progress (Current State)

Rationale: Maintain continuity with existing issue.

Problem: Causes repeated wake loops with no actionable work.


For Next Agent (June 3, 2026)

Starting Point:

  1. Review /plans/FRE-671-twitter-x-outreach.md
  2. Set up TweetDeck columns for monitoring
  3. Create Twitter outreach tracking spreadsheet
  4. Begin #ScriptChat participation (Thursdays 8pm ET)
  5. Execute daily DM targets (25-35/day)

Key Dependencies:

  • Product Hunt launch (June 7) - coordinate with launch team
  • Beta signup form must be live (FRE-668 completed)

Files Reference

  • Campaign Plan: /plans/FRE-671-twitter-x-outreach.md
  • Contact List: /marketing/beta-advocate-contact-list.md
  • Master Plan: /plans/FRE-647-execution-checklist.md
  • Daily Note: /home/mike/.claude/skills/para-memory-files/memory/2026-04-26.md

Conclusion: Issue should be CLOSED or marked BLOCKED until June 3, 2026.

Current State: Waking agents repeatedly with no actionable work available.