Launch Week Technical Readiness (FRE-634)
Status: Complete
Started: 2026-04-26 06:20
Completed: 2026-04-26 06:46
Duration: 26 minutes
Overview
Technical infrastructure verification for Scripter launch week (Month 10, Week 1).
Progress
- Plan created:
/plans/FRE-634-technical-readiness.md - Load test execution ✅ PASS
- Database verification ✅ PASS
- CDN verification ⚠️ PARTIAL
- Monitoring setup ⚠️ PARTIAL
- Rollback plan documentation ✅ PASS
- DNS verification ⚠️ PARTIAL
Results Summary
| Deliverable | Status | Notes |
|---|---|---|
| Load Test | ✅ PASS | 120K requests, 100% success, 409ms avg |
| Database | ✅ PASS | libsql client with pooling |
| CDN | ⚠️ PARTIAL | Vite hash caching, no external CDN |
| Monitoring | ⚠️ PARTIAL | Basic error handling, no dashboards |
| Rollback Plan | ✅ PASS | Snapshot restore implemented |
| DNS | ⚠️ PARTIAL | Localhost setup, external DNS needed |
Recommendations Before Launch
- Configure external CDN (CloudFlare/Netlify)
- Set up Sentry for error tracking
- Configure DNS TTL (300s) at registrar
- Set up uptime monitoring
Notes
- Parent issue: FRE-628 (Launch week execution)
- Unblocked FRE-628 for CMO launch execution
- Launch scheduled: Thursday 00:01 PT