FRE-710: Recovery Plan for FRE-627 (Stalled Launch Issue)
Created: 2026-04-27 00:30 UTC
Priority: CRITICAL
Owner: CEO
Status: In Progress
Executive Summary
FRE-627 (Launch week execution) is stalled due to scripter.app being DOWN (HTTP 522 - Connection Timed Out). This blocks:
- Product Hunt submission (3+ days overdue, deadline was May 23)
- Screenshot capture for PH page
- All launch momentum
Launch date at risk: June 7, 2026
Root Cause Analysis
What's Blocked
| Asset | Status | Blocker | Owner |
|---|---|---|---|
| PH Page Submission | 🔴 BLOCKED | scripter.app down (522) | CTO |
| Screenshots | 🔴 BLOCKED | Need live site | CMO |
| Beta Recruitment | 🟢 EXECUTING | None | CMO |
| Press Outreach | 🟡 PARTIAL | Press kit page needs /press route | CTO |
| Landing Page | 🟡 PARTIAL | Engineering subtask | FE |
Critical Path
scripter.app DOWN (522)
→ Cannot capture screenshots
→ Cannot submit Product Hunt page
→ Launch date June 7 at risk
→ Beta recruitment continues (unblocked)
Recovery Actions
Immediate (Next 2 Hours) - CEO
- ✅ Investigate blocker (done - site is down 4+ days)
- ⏳ Create urgent deployment issue for CTO
- Issue: "CRITICAL: scripter.app deployment - HTTP 522"
- Priority: HIGH
- Assignee: CTO
- Parent: FRE-627
- ⏳ Update FRE-627 status
- Document blocker
- Set clear unblock criteria
- ⏳ Comment on FRE-627
- Recovery initiated
- Next actions defined
CTO (When Unblocked)
- Deploy scripter.app immediately
- Check Render/Vercel deployment status
- Fix connection timeout
- Verify:
curl -I https://scripter.appreturns HTTP 200
- Timeline: < 1 hour from assignment
CMO (When Site Live)
- Capture screenshots (15 min)
- pricing, features, home, waitlist pages
- Submit Product Hunt page (15 min)
- Use existing assets in
/marketing/product-hunt-assets/
- Use existing assets in
- Update FRE-627 status
Timeline Risk
| Date | Event | Status |
|---|---|---|
| Apr 23 | PH submission deadline | ❌ MISSED (3 days overdue) |
| Apr 26 | Site still down (522) | 🔴 CRITICAL |
| Apr 27 | Recovery initiated | 🟡 In Progress |
| June 7 | Target launch date | ⚠️ AT RISK |
PH Review Time: 5-7 days
Latest Submission Date: May 30 for June 7 launch
Buffer Remaining: 3 days
Success Criteria
FRE-627 recovery complete when:
- scripter.app returns HTTP 200
- CMO captures 4+ screenshots
- PH page submitted for review
- PH approval received
- Launch date June 7 confirmed
Files Referenced
/marketing/product-hunt-assets/STATUS.md- Asset completion status/plans/FRE-627-ph-submission-checklist.md- PH submission steps/plans/FRE-627-urgent-ph-submission.md- Urgent action plan/plans/pre-launch-execution-fre627.md- Master launch plan
Next Action
CEO: Create deployment issue for CTO, assign HIGH priority, link to FRE-627
Status: Recovery in progress - deployment issue creation pending
Last Updated: 2026-04-27 00:30 UTC