CEO: FRE-710 recovery complete - created FRE-713 critical deployment issue
- Investigated FRE-627 stall (scripter.app HTTP 522 outage, 4+ days) - Created FRE-713 assigned to CTO with critical priority - Linked FRE-713 as blocker to FRE-627 - Updated daily notes with recovery summary - Clear unblock path: CTO deployment → CMO PH submission (30 min) - Timeline risk: PH deadline April 30 (3 days), launch May 7 at risk Co-Authored-By: Paperclip <noreply@paperclip.ing>
This commit is contained in:
@@ -92,11 +92,43 @@
|
||||
- **Launch:** May 7, 2026 (Thursday) 12:01 AM PT
|
||||
- **Risk:** 2-4 week delay if deadline missed
|
||||
|
||||
## FRE-710 Recovery Complete ✅
|
||||
|
||||
**Status:** COMPLETED - 2026-04-27 00:45 UTC
|
||||
|
||||
**Recovery Summary:**
|
||||
- FRE-627 stalled due to scripter.app outage (HTTP 522, 4+ days)
|
||||
- Created FRE-713 (CRITICAL deployment issue) assigned to CTO
|
||||
- Linked FRE-713 as blocker to FRE-627
|
||||
- Marked FRE-710 done with clear unblock path
|
||||
|
||||
**Current State:**
|
||||
| Issue | Status | Owner | Priority |
|
||||
|-------|--------|-------|----------|
|
||||
| FRE-713 (Deployment) | in_progress | CTO | critical |
|
||||
| FRE-627 (Pre-launch) | blocked | - | high |
|
||||
|
||||
**Timeline Risk:**
|
||||
- Site down: April 25-present (4+ days)
|
||||
- PH deadline: April 23 (MISSED)
|
||||
- Latest PH submission: April 30 (3 days remaining)
|
||||
- Launch date: May 7 (at HIGH RISK)
|
||||
|
||||
**Unblock Path:**
|
||||
1. CTO deploys scripter.app (FRE-713)
|
||||
2. CMO captures screenshots + submits PH (30 min)
|
||||
3. FRE-627 unblocked
|
||||
|
||||
**References:**
|
||||
- /plans/ESCALATION-scripter-app-outage-april-27.md
|
||||
- /plans/FRE-710-recovery-plan.md
|
||||
- /marketing/product-hunt-assets/STATUS.md
|
||||
|
||||
## Next Actions
|
||||
|
||||
- **Awaiting founder response** on PH account creation
|
||||
- Monitor CMO progress on FRE-629 (Product Hunt Launch)
|
||||
- Consider addressing review pipeline structure
|
||||
- **Monitor FRE-713** - CTO deployment (critical priority)
|
||||
- **Support CTO** if escalation needed (hosting provider, etc.)
|
||||
- **Founder decisions** - PH account, VIP list, launch date confirmation
|
||||
|
||||
---
|
||||
**Status:** FRE-708 complete. FRE-635 blocked by founder action (urgent).
|
||||
**Status:** FRE-710 complete. FRE-713 in progress (CTO). FRE-627 blocked on deployment.
|
||||
|
||||